March 2006
Project Focus - Sharkham Village Residential
Development, Devon
THE
PROBLEM
Millwood Homes (Devon) Limited, a developer from Newton
Abbot, Devon contacted RIW to seek advice on how best
to protect a proposed development in Brixham against
water ingress and Radon emissions. The Sharkham Village
development was to be constructed on a sloping site
and consisted of a number of new town houses that stepped
up a slope thus creating a series of single-sided basements.
As the development steps up the hill a suspended beam
& block floor was selected rather than a ground
bearing slab.
Millwood Homes were keen to develop a tanking detail
that would conform to the Building Regulations and provide
adequate protection against the potential for ingress
of water and radon emissions. Whilst liaising with Millwood
Homes, RIW understood that the proposed detail not only
needed to prevent the ingress of water, water vapour
and Radon but that it also needed to be as simple as
possible to install on site due to the consequences
should the waterproofing prove inadequate. If possible,
the proposed detail should avoid sequencing problems
to avoid unnecessary delays to the construction programme.
THE SOLUTION
Mark Anstee of the RIW
Technical Department proposed the use of
RIW
Cavity Drain as shown on detail SD
/ Typical / 007 which can be linked in
to the DPM with RIW
Sheetseal 9000 DPC. This detail ensures
continuity between each element of the waterproofing
design and encourages cross ventilation through the
cavity to ensure the Radon emissions disperse freely.
The use of RIW Cavity Drain vertically also eliminates
any direct water pressure allowing water that passes
through the vertical structure to drain freely in to
the void under the block & beam floor. Also if wall
ties are required to tie back the internal masonry wall
they can be screwed into the brick plugs used to fix
the Cavity Drain system thus avoiding the necessity
to puncture the membrane and break the waterproofing/Radon
integrity.
Nigel White of Millwood Homes
said “We
wanted a solution that was straight forward to build
and would not delay progress on site, but we didn’t
want to have separate waterproofing and Radon barriers.
We initially considered an external tanking system but
this could not easily be linked to the Radon barrier.
We were therefore very pleased when we contacted RIW
and they suggested the Cavity Drain system. This resolved
all the problems and allowed progress to continue unhindered
on site as all the tanking could be installed after
the in-situ concrete foundations and retaining walls
had been constructed.”
PROJECT DETAILS
| Project: |
Town Houses,
Sharkham Village, Brixham, Devon |
| Developer: |
Millwood Homes (Devon) Limited |
| Specifier: |
Millwood Homes (Devon) Limited |
| Products
used: |
RIW
Cavity Drain
RIW
Sheetseal 9000 DPC |
|