August 2007
Project Focus - Avon & Somerset
Police HQ
‘Design
should be considered at an early stage’
The new headquarters completed in the
mid 1990’s for Avon & Somerset Police in Portishead
is a typical example of the importance of considering
waterproofing at an early stage in new building design.
RIW were contacted by Bruges Tozer to put forward their
recommendations for damp proofing the ground floor slabs
of the HQ building.
The installation was particularly interesting as the
architect wanted to achieve a simple and uniform installation
without altering the waterproofing needed for the varying
conditions.
The different elements that needed to be waterproofed
included: ground floors with finishes ranging from carpet
to vinyl, computer rooms with raised access flooring
and a lecture theatre below ground level requiring tanking.
RIW
Toughseal was applied in situations where
the traditional method of using a screed to protect
the waterproof membrane could not be used. In areas
where raised
access floors were required the pedestals
where adhered directly to the membrane, avoiding the
need for mechanical fixings and inherent danger of penetrating
the membrane.
Where suspended
wood flooring on wood battens were
specified, the membrane was applied to the concrete
floor slab, enabling the battens to be fixed directly
to the slab.
In both of these situations the elimination of a screed
provided benefits in terms of cost and time while allowing
the continuity of the membrane to be unaffected.
The ground floor also included pre-cast
plank construction. In this situation, movement between
individual components was considered a possibility.
To overcome this, RIW’s
Flexiseal was specified.
Flexiseal
is a rubber-like flexible liquid
membrane that can accommodate up to 4-5mm of movement
without failure of the membrane (Contact our Technical
Department on 01344 397777 for more advice).
In more traditional situations where
a screed was provided, RIW
LAC was used as the damp proof membrane.
At all stages care was taken to ensure that continuity
of the membranes was achieved despite the differing
construction techniques and finished flooring requirements.
The nature of the construction programme required RIW’s
technical staff to respond very quickly to the requests
for details with information being faxed between the
two companies.
RIW also checked all specifications
and visited the site to ensure the products were being
applied correctly.
|