November 2007
Tanking or Damp-proofing at
Ground Level?
When
is simply using traditional and cost effective Damp
Proof Membranes (DPM) such as polythene
below a concrete slab at ground level not acceptable
and under what circumstances would a more robust tanking
solution be required?
Building Regulations Approved Document
C (Site preparation and resistance to contaminants and
moisture) states; ‘floors next the ground
should resist the passage of moisture to the upper surface
of the floor’.
NHBC Standards and Technical Requirements
Document states; ‘Where habitable rooms are
wholly or partly below ground level, they require waterproofing,
usually in the form of tanking. Polythene or Visqueen
will not be acceptable to NHBC as a tanking
material’.
BS8102:1990 (Code of practice for protection
of structures against water from the ground) states;
‘Almost all structures are likely to be subjected
to water pressure at some point of their life’.
The above statements show that serious
consideration must be given to the design considerations
outlined below before choosing the most suitable waterproofing
strategy / products. The overall costs of installing
the waterproofing can be less than 1% of the overall
contract value, however it could cost as much as 10
to 12% of the overall contract value to rectify any
failure that may occur.
The Building Regulations Approved Document C outlines
a number of design considerations that should be taken
in to account before you build your waterproofing strategy;
1. the presence of contaminants and
gases in the ground,
2. the level of the water table
3. sub-soil drainage, and
4. the resistance to moisture
Each of these will have a significant influence on
the form and selection of the waterproofing.
1. The presence of contaminants
and gases in the ground
A wide range of solid, liquid and gaseous
contaminants can arise on site and will be identified
in the soil investigation. Armed with this information
the potential risk can then be evaluated. Some membranes
will provide an
effective barrier to contaminants and gases such as
Radon, Methane and Carbon Dioxide however,
the importance of the membrane maintaining its integrity
is often over looked.
CIRIA guidance publication 659 (Assessing
risks posed by hazardous gases to buildings) states
that ‘Membranes should be based on their performance
characteristics and ability to survive the construction
phase’. It is widely accepted that some membranes
such as 1200g Polythene, the minimum thickness for a
gas resistant membrane on low risk sites, is unlikely
to achieve the required level of robustness.
2. The level of the water table
The severity of the risk falls in to
three categories;
Permanently low –
No significant risk of percolating water building up
to create a hydrostatic head of water against the structure
(free draining),
Permanently high –
Water table is close to or above the lowest level of
the concrete floor slab creating a high risk of hydrostatic
head of water against the structure, and,
Variable or perched
– Water table may become temporarily high seasonally
or during periods of heavy rainfall thus creating a
risk of hydrostatic head of water against the structure
(the severity of risk will depend on how high and for
how long the water table remains perched).
Therefore, it could be argued that
where a risk of a hydrostatic head of water pressure
being applied to the DPM exists, then a suitable ‘tanking
system’ should be considered in preference to
a DPM.
3. Sub-soil drainage
Sub-soil drainage should be provided
where (i) there is a risk that groundwater beneath or
around the building could adversely affect the stability
and properties of the ground and (ii) contaminants are
present in the ground, the
sub-soil drainage will help prevent the risk of water-borne
contaminants being transported in to the building or
its foundations.
4. Resistance to moisture
It is essential that the structural elements, whether
wholly / partly below or at ground level, resist moisture
from surrounding ground. This is generally achieved
with the inclusion of a waterproof membrane and by providing
a means of drainage, where necessary, that will allow
moisture to disperse from the structure.
Selection of the waterproof system
Selecting an appropriate membrane has
to be more than a cost engineering exercise, and all
of the above design considerations must be taken into
account to ensure the right system is selected.
It is important to understand the attributes
of each product, but it is essential to understand
the product's limitations.
For instance, polythene which is commonly
used below a concrete slab as a DPM, is cost effective
and easily installed but is extremely susceptible to
damage, un-bonded and not considered suitable as a tanking
system. It is also suggested in CP102:1973 that polythene
is not suitable below a concrete slab to be covered
with sensitive finishes such as Vinyl, Lino and timber.
Therefore, as suggested in the Building
Regulations and the NHBC technical standards, polythene
should only be used as a DPM
in low risk free draining ground conditions and not
for habitable rooms wholly or partially below ground.
There are many other generic waterproofing
systems available for use as a DPM in the more high
risk ground conditions and where the habitable areas
are wholly or partially below ground, such as; Bitumen
coatings, self
adhesive sheet membranes, Geo-composite
bentonite membranes, Epoxy
coatings, Flexible
polyurethane coatings.
As with polythene, all of these systems have ‘attributes
and limitations’ and should be considered individually
to assess the products suitability for specific forms
of floor and wall construction, for instance;
Ground bearing slab
Consider placing the DPM
on top of the slab, as the membrane;
• is less likely to be subjected
to significant hydrostatic pressure
• can be applied later in the project in a controlled
‘dry’ environment
• is less susceptible to damage during the floor
construction, thus retaining it’s integrity
• protects sensitive floor finishes from moisture
in the concrete slab
Suspended slab in contact with the
ground
Susceptible to the ground falling away from beneath
the slab, the membrane;
• can be applied on top of the slab, as above,
or
• must
have the ability to mechanically or chemically bond
to the underside of the slab
• must be capable of retaining its integrity and
have sufficient toughness to remain undamaged during
the floor construction phase (CP102:1973 & CIRIA
659).
• should be sufficiently versatile to be installed
around piles, pile caps and ring beams without the need
for complex and unnecessarily complicated detailing
Concrete slab wholly or partly below
ground
Where the structure has one of more vertical retaining
walls, the membranes;
• should be recognised as ‘tanking’
systems’ (polythene is not acceptable)
• continuity must be maintained between the horizontal
and vertical membranes
• performance can be enhanced with the provision
of effective sub-soil drainage
To conclude, a polythene DPM may be
a cost effective damp-proofing solution in low risk
ground conditions, however, should it prove ineffective,
the cost implications to rectify the problem can be
significant.
Therefore, it is essential to understand that Building
Regulations Approved Document C and other widely used
technical guidance notes / standards (NHBC, CIRIA, BS8102,
CP102) outline that there are many situations where
a more high performance and robust ‘tanking membrane’
is required to protect the structure against moisture
and contaminates from the ground especially if;
• Contaminates and gases are present in the ground
• The water table is permanently high, variable
or perched
• The surrounding ground conditions are not considered
free draining
• The habitable room is wholly or partly below
ground level
The RIW
Technical Department can be contacted on
01344 397777 to advise on the selection of the most
appropriate waterproofing strategy for your structure,
or just follow the links provided in this technical
newsletter.
Please note: CIRIA 659 is currently
under review.
|